Cloud · 2024
Data centre to cloud migration
Investment firm · UAE
Moved a twelve-year-old on-premise estate to AWS with UAE data residency and no unplanned downtime.
-38%
Annual infrastructure cost
0
Unplanned downtime minutes
The challenge
The firm's core systems ran on ageing hardware under a lease that was ending, with regulatory requirements that client data stay inside the UAE.
Our approach
- 01
Inventoried every workload and sorted it into rehost, rebuild or retire, then agreed the list with the compliance team before touching anything.
- 02
Rebuilt the environment in Terraform in the me-central-1 region and ran both estates side by side for eight weeks.
- 03
Cut over service by service on weekends with a tested rollback for each one.
The result
Annual infrastructure spend fell 38% and the estate is now reproducible from code. The migration completed with no unplanned downtime and passed the regulator's residency review first time.
- AWS
- Terraform
- Kubernetes
- Grafana